Tying a temporary mast guy to a soil deadman, what must precede daily lifting reliance?

Choices

  • (A) Guess capacity from topsoil appearance
  • (B) Proof-test or pull-test to design capacity with logged results per temporary works plan
  • (C) Hand-tie rope without gauge
  • (D) Ignore rain effects on anchor soils

Correct answer: (B)

Proof-test or pull-test to design capacity with logged results per temporary works plan

Explanation

Proof loads reveal loose anchors before incidents.