Before certifying an engineered tandem pick exceeding published chart limits temporarily, what record set best embodies accepted lift-plan governance?
Choices
- (A) Single visual weight guess
- (B) Engineered loads + rigging layout + crane chart cut sheets + meteorological Holds
- (C) Skip fabrication engineering because unrelated engineer exists onsite
- (D) Waive HSE because delay is brief
Correct answer: (B)
Engineered loads + rigging layout + crane chart cut sheets + meteorological Holds
Explanation
Load + meteorology dossiers underpin signed lift approvals.