Following clustered surface porosity in a field weld called out by QA, when should re-inspection generally be rerun under disciplined site choreography?

Choices

  • (A) Randomly after another coat cures without QA concurrence
  • (B) Before sign-off QC prior to coatings, with rework executed per revised WPS if required
  • (C) After six unrelated months elapsed
  • (D) Only once owner warranty lapses

Correct answer: (B)

Before sign-off QC prior to coatings, with rework executed per revised WPS if required

Explanation

Pre-coating verification prevents concealment defects.