When neighboring sensitive instrumentation complains about nearby pile-driving noise/vibration during foundation works, what is the most defensible first engineering response keyed to standard site controls?
Choices
- (A) Ignore readings because piles are temporary
- (B) Compare vibration/noise envelopes to contractual limits plus approved working windows and setbacks
- (C) Cancel foundations to alleviate traffic jams
- (D) Relocate owner equipment covertly without notice
Correct answer: (B)
Compare vibration/noise envelopes to contractual limits plus approved working windows and setbacks
Explanation
Contract thresholds + documented windows steer mitigation before escalation.