Before back-propping/loading a young slab, the most common shoring/loading safeguard threshold is (generic practice):

Choices

  • (A) 24 hours
  • (B) 75% of 28-d f꜀′ on day 0
  • (C) Reach ~50% of 28-d strength (often ~7d) or project rule
  • (D) Rely on dead load estimate only

Correct answer: (C)

Reach ~50% of 28-d strength (often ~7d) or project rule

Explanation

Reshore/shoring release rules site-specific; many specs target ~50% f꜀′ (often ~7d) or similar.