← Back to question bank

The “ventilation rate” procedure in ASHRAE 62.1 is distinct from the IAQP in that the rate procedure prescribes which starting point (conceptual)?

Choices

  • (A) Only IAQP is allowed in offices
  • (B) Chemical inventory only
  • (C) No minimum OA in hospitals
  • (D) Prescribed minimum OA rates by occupancy class (plus area), then other adjustments, vs contaminant target approach in IAQP

Correct answer: (D)

Prescribed minimum OA rates by occupancy class (plus area), then other adjustments, vs contaminant target approach in IAQP

Explanation

62.1: VRP vs IAQP paths, local adoption.

Back to question bank →

Question 32 of 80